PRACTICAL end of the exercise students should be able

PRACTICAL GUIDE FOR ELECTRICAL INSTALLATION OFBUILDING SYSTEM(EEC 129)  COMPILEDBYODUBONAISMAIL OKANLAWON  ELECTRICALELECTRONICS DEPARTMENTYABACOLLEGE OF TECHNOLOGY             CONTENTSWORKSHOP PRACTICE 01: CABLE JOINTSWORKSHOP PRACTICE 02: WIRING TECHNIQUES WORKSHOP PRACTICE 03: POWER DISTRIBUTIONWORKSHOP PRACTICE 04: TESTING OF ELECTRICAL INSTALLATION WORKSHOP PRACTICE 05: ELECTRICAL SOLDERINGWORKSHOP PRACTICE 06:ELECTRIC MOTOR INSTALLATION             WORKSHOP PRACTICE 01:TITLE: CABLE JOINTS Aims:At the end of the exercise students should be able to understand differentmethods of joining electrical cables and their applications Materials8mm2 service cableToolsCutting plierScraping knifeNose plier Type 1: Knottedtap.Application:Thisis used where the tap wire is under heavy tensile stress.  Diagram Step1: Removethe insulation of the running wire as shown below for a length of about 2.

5cm.         Step2:Remove the insulation of the branch wire for a length of about 7.5cm      Step3: Gentlyclean the conductors with the help of a double zero sand paper.

Best services for writing your paper according to Trustpilot

Premium Partner
From $18.00 per page
4,8 / 5
4,80
Writers Experience
4,80
Delivery
4,90
Support
4,70
Price
Recommended Service
From $13.90 per page
4,6 / 5
4,70
Writers Experience
4,70
Delivery
4,60
Support
4,60
Price
From $20.00 per page
4,5 / 5
4,80
Writers Experience
4,50
Delivery
4,40
Support
4,10
Price
* All Partners were chosen among 50+ writing services by our Customer Satisfaction Team

Step4:First knot the wire as shown below     Step5: Makefive to eight turns of the branch wire and round off the conductor end with thehelp of a pliers or mallet. Type 2: Plaintap joint.Application:Thisis used where the tap wire is under considerable tensile stress circuit.

 Diagram Step1: Removethe insulation of the running wire as shown below for a length of about 2.5cm.      Step2:Remove the insulation of the branch wire for a length of about 7.5cm  Step3: Gentlyclean the conductors with the help of a double zero sand paper.Step4: Nowkeeping the branch wire at 900 to the running wire, and withinsulation of both wires near to each other, make a neck turn as shown in thediagram which guides against the sleeping of the joint under pressure. And makefive to eight turns.

      Step5: Nowround off the conductor end with the help of a pliers or mallet.     Type3: Cross joint. Application:Thesame application is done as in plain tap and the only difference is that thistap is a combination of two plain taps place side by side with each other. Diagram      Type 4: WesternUnion Short-tie Splice. Application: This is the mostwidely used splice or joint in interior wiring installation to extend the lengthof wire from one point to another.

Diagram  Step1: Crossthe two bear wires at a distance of about 2cm from insulation of either of thewire, the wires across on neck turned as shown.      Step2: Thecrossing on neck turn of the conductors prevents the two wires being separatedout under a pressure. Now with he help of the four fingers and thumb or withpliers make five to eight turns.        The remaining excess of theconductors should be cut away with pliers.                   WORKSHOP PRACTICE 02;WIRING TECHNIQUESAim: At the end of the exercise, students should beable to:1.

                 Install a Single light point controlled by a one-way switch 2.                 Install Two light points controlled by a one-way switch 3.                 Install Two light points controlled separately by two one-wayswitches4.                Install a ring circuit5.                Install an Earth Leakage Circuit Breaker(ELCB.)  1.

                Materials/Items 1.                5A 1-gang, 1-way switch EarthLeakage Circuit Breaker13ASwitch socket outlet x4 (pattress) Ceilingrose x 4Jointbox x 5 ¾screws 5 packets Bulkedclips 20 packets 13Aplugs x 5 Cables1.5 mm2 x 2 PVC         , 2.5mm2x 3 PVC, 0.5mm2 x 2 (flexible cord)                                                          2.

3     Diagrams (i)                Singlelight point controlled by a one-way switch N L S LAMP       (ii)              Twolight points controlled by a one-way switch N L S LAMP 1 LAMP 2       (iii)            Twolight points controlled separately by two one-way switches N L LAMP 1 LAMP 2 S1 S2        2.5     Precaution2.6     Conclusion    EXPERIMENT 03:3.0    Title: power Distribution3.1     Aim:Atthe end of the exercise, students should be able to distribute power in a consumerpremises employing;1.                Single phase 2.                Three-phase four-wire systems.

3.2    Material/Itemsi.        ConsumerControl Unit:          I-Phase3-Phaseii.       1.5mm2 x 2 co res PVCiii.      2.

5mm2x 3 cores PVCiv       4.0mm2x 3 cores PVCv.      6.

0mm2 x 3 cores PVC 3.3     Descriptions/Diagram (attached)3.4     Precaution3.

5    Conclusion  EXPERIMENT 04:4.0    Title: Testing of ElectricalInstallation 4.1     Aim:At the end of the exercise, students should be ableto carry out: 1.

                Verification of polarity;2.                Insulation test; 3.                Earthing test 4.                Test of Ring Circuit Continuity 4.2     Materials/items/Equipmenti.        Test boardii        Ohmmeteriii.

      Meggeriv.      Indicator tester (Neon Tester) 4.3    Diagrams(attached) 4.4     Description 4.5    Precaution 4.6    Conclusion                          EXPERIMENT05:5.

0    Title: Electrical Soldering5.1     Aim: At the end of the exercise, the studentsshould be able to carry out; i.        Solderingbit methodii.       Stick”Methodiii.      Potand Laddie Method.

(Metal) 5.2    Materials/Equipmenti.        Pliersii.       Sharp knifeiii.      Soldering bitiv.      Fluxv.

       Blow lampvi.      Solder vii.     Rubber Tapeviii.    Cambric tape (empire tape    ix. Black Insulating tape. 5.

3     Description5.3.1  Soldering bit methodi.        Smearjoint with resinous fluxii.       Applytinned bit under the joint the heat penetrates it.iii       Apply stick of solder to the joint until thesolder flows freely through it5.32   Stick methodi.

        Heat joint with a b low Iampii.       Apply flux to the jointiii.      Apply stick of solder to the joint until thesolder Hows freely through it. 5.3.

3  Pot andladdle method (heavy duty)i.        Heatsolder pot until the solder is running freely.ii.

      When the solder as reached workingtemperature, transfer from the pot with a ladle. iii.      Asthe solder is being pour over the prepared joint, it is caught by another ladleplaced under the joint. iv.      This action is repeated until the solderpenetrates the joint,5.4    Precaution 5.5     Conclusion              EXPER1MENT 06: 6.0     Title:Electric Motor Installation 6.

1    Aim: At the end of theexercise, students should be able to wire Electric motors using:i.        Direct-On-LineStarterii.       AutoTransformer Starter iii.      ResistanceStarter iv.

      Star-DeltaStarter 6.2     Material/Itemsi.        Contractorsii.       IsolatorHi.     Delayon-timer/delay off-timeriv.      Overload relayv.       Limitingswitchvi.      Currenttransformer, V,vii.

     Ammeter,voltmeter, frequency meterviii.   Start/Stop buttonix       Pilotlamps (red, green, amber) 6.3     Diagrams(attached) 6.4     Description(operation) 6.5     Precaution 6.6    Conclusion